Table 13.3
Consider the following MPS, BOM, and inventory data. You will need a blank MRP record to answer the question(s) .
Master Production Schedule: the following table shows the MPS start quantities.
Week
Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
Item
-Use the information in Table 13.3.Which one of the following statements about item F is TRUE?
A) The first planned order release is for 205 units in week 3.
B) Its first planned receipt is for 215 units in week 4.
C) There will be exactly one action notice, which calls for the release of a new order.
D) There will be exactly one action notice, which calls for the delay of the scheduled receipt until week 2.
Correct Answer:
Verified