Mohammed Is Monitoring the Diameter of Bolts Being Produced on One

Question 1

Multiple Choice

Mohammed is monitoring the diameter of bolts being produced on one of his assigned production lines.During this process,he notices one,single measurement that jumped above the upper control limit.He immediately adjusts the alignment on several machines to address the problem.Mohammed has likely


A) committed a type II error.
B) made a good decision.
C) committed a type I error.
D) committed both a type I and type II error.

Correct Answer:

verifed

Verified