Which of the following statements regarding CPM is TRUE?
A) The critical path is the shortest of all paths through the network.
B) The critical path is that set of activities that has positive slack.
C) Some networks have no critical path.
D) All activities on the critical path have their LS equal to the maximum EF of all immediate predecessors.
E) All activities on the critical path have their ES equal to their LF.
Correct Answer:
Verified
Q46: The network analysis method that allows activity
Q47: A simple CPM network has five activities,
Q48: Identify, in order, the six steps basic
Q49: The difference between AON and AOA networks
Q50: The _ is the computed longest time
Q52: Activity R on a CPM network has
Q53: A simple CPM network has three activities,
Q54: The critical path can be determined by
Q55: The _ is a project management technique
Q56: The main difference between PERT and CPM
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents