Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 22. Which of the following is definitely TRUE?
A) R is critical and has zero slack.
B) R has no slack but is not critical.
C) The set of times cannot all be possible.
D) N is a critical activity.
E) S is a critical activity.
Correct Answer:
Verified
Q47: A simple CPM network has five activities,
Q48: Identify, in order, the six steps basic
Q49: The difference between AON and AOA networks
Q50: The _ is the computed longest time
Q51: Which of the following statements regarding CPM
Q53: A simple CPM network has three activities,
Q54: The critical path can be determined by
Q55: The _ is a project management technique
Q56: The main difference between PERT and CPM
Q57: Every network has at most one critical
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents