A way to improve estimates on future projects is to collect and archive data on past project estimates and actuals. Creating ___________ for estimating is a way to achieve this goal.
A) time and cost databases
B) history databases
C) estimating and forecasting databases
D) structured databases
E) Any of these alternatives are correct.
Correct Answer:
Verified
Q65: The top-down method for estimating project time
Q66: Estimates should be made based on _
Q67: Costs that are associated with time devoted
Q68: Mega projects are large-scale, complex ventures that
Q69: The salary of the project manager and
Q71: The information necessary to conduct a bottom-up
Q72: The preferred method for situations where the
Q73: The approach to estimating project time and
Q74: Consider a five-mile-long railroad tunnel. Tunnel experts
Q75: A project estimator is working on estimates
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents