The cost variance for a project is calculated by
A) EV − AC.
B) AC − SV.
C) PV − EV.
D) CV − EV.
E) EV − PV.
Correct Answer:
Verified
Q37: The earned value system starts with the
Q38: If the cost of labor and materials
Q39: In monitoring project time (schedule) performance, actual
Q40: The schedule variance is the best way
Q41: Which of the following methods of variance
Q43: A project manager receives the following information
Q44: The chief financial officer receives the following
Q45: A program financial accountant learns that a
Q46: Which performance index is the most potentially
Q47: When someone familiar with each task estimates