Question 41
Multiple Choice
Which of the following methods of variance analysis is the best indicator of how far off the budget a project will be at completion?
Question 42
Multiple Choice
The cost variance for a project is calculated by
Question 43
Multiple Choice
A project manager receives the following information on his project: PV = 4,500, AC =4,000, EV = 5,000. How well is the project doing in terms of budget?
Question 44
Multiple Choice
The chief financial officer receives the following information on a project: PV = 10,000, EV = 12,000, AC = 8,000, BAC = 20,000, EAC = 13,333. How is the project doing in terms of schedule?
Question 45
Multiple Choice
A program financial accountant learns that a project is currently earning $1.15 for each dollar actually spent. The accountant is able to determine this by looking at the
Question 46
Multiple Choice
Which performance index is the most potentially misleading?
Question 47
Multiple Choice
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the