The chief financial officer receives the following information on a project: PV = 10,000, EV = 12,000, AC = 8,000, BAC = 20,000, EAC = 13,333. How is the project doing in terms of schedule?
A) More work has been done than planned
B) Less work has been done than planned
C) The same amount of work has been done than planned
D) The project has cost more than planned
E) There is not enough information to draw a conclusion
Correct Answer:
Verified
Q39: In monitoring project time (schedule) performance, actual
Q40: The schedule variance is the best way
Q41: Which of the following methods of variance
Q42: The cost variance for a project is
Q43: A project manager receives the following information
Q45: A program financial accountant learns that a
Q46: Which performance index is the most potentially
Q47: When someone familiar with each task estimates
Q48: Of the following costs, which are NOT
Q49: Which of the following methods will measure
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents