At the Beginning of the Project, It May Not Be

Question 38

Multiple Choice

At the beginning of the project, it may not be possible to estimate the costs for all activities with a level of confidence regarding their accuracy.This is especially true for


A) projects with a short term.
B) longer-term projects.
C) projects that are similar to ones completed by the organisation before.
D) projects with activities that are serially related.

Correct Answer:

verifed

Verified

Unlock this answer now