The is the amount that was actually spent to achieve the work that was scheduled to be performed up to that point in time.
A) total budgeted cost (TBC)
B) cumulative budgeted cost (CBC)
C) cumulative actual cost (CAC)
D) cumulative earned value (CEV)
Correct Answer:
Verified
Q27: The _ for the entire project or
Q32: When the budgets for all the work
Q34: Often, the sum of the initial estimated
Q38: At the beginning of the project, it
Q38: It may be easier to estimate the
Q42: Consider a project that involves painting five
Q47: Costs are _ when an item is
Q52: Another indicator of cost performance is cost
Q54: As data are collected on _, including
Q56: The cost performance index (CPI)is a measure