Consider a project that involves painting five similar houses over ten weeks (one house every two weeks) for a total budgeted cost of R200 000.The budget is R4 0000 per house.At of the end of week 5, you determine that R100 000 has actually been spent and three houses have been painted completely.What is the earned value of the project?
A) R100 000
B) R120 000
C) R40 000
D) R200 000
Correct Answer:
Verified
Q27: The _ for the entire project or
Q32: When the budgets for all the work
Q34: Often, the sum of the initial estimated
Q38: At the beginning of the project, it
Q41: The is the amount that was actually
Q47: Costs are _ when an item is
Q47: Determining the earned value involves collecting data
Q52: Another indicator of cost performance is cost
Q54: As data are collected on _, including
Q56: The cost performance index (CPI)is a measure
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents