In Order to Determine Overall Progress on Her Current Project

Question 181

True/False

In order to determine overall progress on her current project, production manager Michelle often refers to a bar graph that shows what activities are being worked on, and how much of each task has been completed on a daily basis. Michelle is using a Gantt chart.

Correct Answer: