At the End of the Third Week of a Project

Question 211

Multiple Choice

At the end of the third week of a project, the actual cost of work performed is $7000 USd and the budgeted cost of work performed is $8000 USd. Which of the following is true?


A) The project is under budget.
B) The project is budget incorrect.
C) The project has been back-end loaded.
D) The project is over budget.