All of the Following Are True About the Post Construction

Question 210

Multiple Choice

All of the following are true about the post construction phase EXCEPT:


A) The owner is responsible to update the record copy drawings to reflect "as-built" documents.
B) The contractors are resolving issues identified on the punch lists.
C) The architect is involved in final acceptance and contract closeout activities.
D) The construction manager is coordinating removal of construction equipment and job trailers.