All of the following are true about the post construction phase EXCEPT:
A) The owner is responsible to update the record copy drawings to reflect "as-built" documents.
B) The contractors are resolving issues identified on the punch lists.
C) The architect is involved in final acceptance and contract closeout activities.
D) The construction manager is coordinating removal of construction equipment and job trailers.
Correct Answer:
Verified
Q205: Which area of project management covers the
Q206: A building has six floors plus a
Q207: What element is typically NOT part of
Q208: A building has six floors plus a
Q209: You are designing a building with a
Q211: At the end of the third week
Q212: The headend has several audio-video playback devices
Q213: Exhibit: The following diagram represents what type
Q214: Exhibit: If a work breakdown structure (WBS)
Q215: Active video converters are required for what
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents