Solved

A Project Manager Provides Status Reports to a Customer on a Biweekly

Question 218

Multiple Choice

A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project. Which of the following are critical for the project manager to provide?


A) Cost, schedule, organizational chart, and risks/issues
B) Risks/issues, cost, RACI chart, and action items
C) Schedule, cost, risks/issues, and milestones
D) Action items, organizational chart, schedule, and NDA

Correct Answer:

verifed

Verified

Unlock this answer now