A senior manager asks a project manager for an estimated budget on a new project. Which of the following is the BEST step for the project manager to take?
A) Tell the senior manager the estimation is not available yet.
B) Use the budget from a similar project to generate estimates.
C) Ask a SME for an opinion and propose an estimate.
D) Gather the team to immediately generate estimates.
Correct Answer:
Verified
Q214: Which of the following measurements would give
Q215: A business has implemented a new online
Q216: A new stakeholder has joined the project
Q217: Which of the following are characteristics of
Q218: A project manager provides status reports to
Q220: Which of the following job roles is
Q221: A department manager asks a project manager
Q222: A project manager does not have enough
Q223: A company hires a number of interns
Q224: A company has hired a new project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents