A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?
A) Fast-track the tasks.
B) Utilize positive float.
C) Crash the schedule.
D) Remove the critical path
Correct Answer: