A project sponsor is reviewing the project dashboard and does not understand what a CPI of 0.87 and an SPI of 1.02 indicate. Which of the following describes the project status?
A) The project is over budget and behind schedule.
B) The project is under budget and ahead of schedule.
C) The project is over budget and ahead of schedule.
D) The project is under budget and behind schedule.
Correct Answer:
Verified
Q501: A project task has been completed ahead
Q502: A project manager learns that a key
Q503: A company just announced all third-party vendors
Q504: A project manager noted there were many
Q505: An American publisher is participating in a
Q507: Analogous estimating was used earlier in a
Q508: A project manager detects low performance from
Q509: A project manager has set aside a
Q510: A project manager wishes to track a
Q511: The supervisor asks an engineer to be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents