A project manager noted there were many possible features that could be incorporated into a project, and the customers wavered about whether to include particular features. Which of the following is the BEST approach to ensure appropriate delivery of the project?
A) In one section of the project charter, specify which features are included in the project, in another section, specify which features are not included in the project.
B) The scope statement should enumerate which features are included in the project and which features are not included in the project.
C) At the beginning and end of every meeting, the project manager should consistently remind the project team which features are included in the project and which features are not included in the project.
D) The project requirements document lists all the features that are included in the project, and the project manager diligently ensures that features not included in the project are not included in the MOU with the customer.
Correct Answer:
Verified
Q499: Two parties are beginning conversations regarding the
Q500: Which of the following inherently affects quality
Q501: A project task has been completed ahead
Q502: A project manager learns that a key
Q503: A company just announced all third-party vendors
Q505: An American publisher is participating in a
Q506: A project sponsor is reviewing the project
Q507: Analogous estimating was used earlier in a
Q508: A project manager detects low performance from
Q509: A project manager has set aside a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents