If the Length of the Critical Path Is 25 Weeks

Question 64

Multiple Choice

If the length of the critical path is 25 weeks, what is the probability that the project will be completed on or before 22 weeks?


A) greater than 20 percent but less than 25 percent
B) greater than 25 percent but less than or equal to 35 percent
C) greater than 80 percent but less than or equal to 85 percent
D) greater than 85 percent