If the length of the critical path is 25 weeks, what is the shortest project due date if the project manager wants at least a 98 percent probability that the project will be completed on or before the due date?
A) less than or equal to 25 weeks
B) greater than 32 weeks but less than 33 weeks
C) greater than 33 weeks but less than or equal to 35 weeks
D) greater than 25 weeks but less than 32 weeks
Correct Answer:
Verified
Q60: Using the second diagram above or using
Q61: Using the information shown in the following
Q62: Using the information shown in the previous
Q63: Using the information shown in the previous
Q64: If the length of the critical path
Q66: Using the data supplied in the
Q67: Using the data supplied, what is the
Q68: Using the data supplied, if a decision
Q69: Using the data supplied, which activity should
Q70: If activity E is reduced by 1
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents