The difference between the total float and free float is called
A) Duration
B) Interfering float
C) Critical activity
D) None of the above
Correct Answer:
Verified
Q8: Form no .........is used for material at
Q9: Mobilization advance
A)Shall be 2 to 5 %
Q10: PERT analysis is based upon
A)Optimistic time
B)Pessimistic time
C)Most
Q11: The time activity consumes in most adverse
Q12: The time activity consumes in normal conditions
Q14: The critical path is
A)The longest path of
Q15: The float of critical activity is always
A)Maximum
B)Minimum
C)Zero
D)None
Q16: A dummy activity in a network
A)Is represented
Q17: Activity starts from
A)Head event
B)Tail event
C)Dual role event
D)None
Q18: Which of the following is an activity
A)Excavation
B)Curing
C)Laying
Unlock this Answer For Free Now!