The critical path is
A) The longest path of the network
B) The shortest path of the network
C) The average duration path of the network
D) None of the above
Correct Answer:
Verified
Q9: Mobilization advance
A)Shall be 2 to 5 %
Q10: PERT analysis is based upon
A)Optimistic time
B)Pessimistic time
C)Most
Q11: The time activity consumes in most adverse
Q12: The time activity consumes in normal conditions
Q13: The difference between the total float and
Q15: The float of critical activity is always
A)Maximum
B)Minimum
C)Zero
D)None
Q16: A dummy activity in a network
A)Is represented
Q17: Activity starts from
A)Head event
B)Tail event
C)Dual role event
D)None
Q18: Which of the following is an activity
A)Excavation
B)Curing
C)Laying
Q19: Earliest start time of activity equals to
A)TE
Unlock this Answer For Free Now!