Question 30

Multiple Choice

The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
The table provides a project with the task lengths (in days)  and precedence requirements, as well as the three time estimates.    -Calculate expected completion time for Task D. A) 3.08 B) 7.03 C) 3.00 D) 1.97 E) 6.93
-Calculate expected completion time for Task D.


A) 3.08
B) 7.03
C) 3.00
D) 1.97
E) 6.93