The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
-Calculate the standard deviation of the project's expected completion time.
A) 0.583
B) 0.417
C) 0.342
D) 0.632
E) 0.232
Correct Answer:
Verified
Q29: The table provides a project with the
Q30: The table provides a project with the
Q31: The table provides a project with the
Q32: The table provides a project with the
Q33: The table provides a project with the
Q35: The table provides a project with the
Q36: The table provides a project with the
Q37: The table provides a project with the
Q38: The table provides a project with the
Q39: The table provides a project with the