Solved

The Table Provides a Project with the Task Lengths (In

Question 34

Multiple Choice

The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
The table provides a project with the task lengths (in days)  and precedence requirements, as well as the three time estimates.    -Calculate the standard deviation of the project's expected completion time. A) 0.583 B) 0.417 C) 0.342 D) 0.632 E) 0.232
-Calculate the standard deviation of the project's expected completion time.


A) 0.583
B) 0.417
C) 0.342
D) 0.632
E) 0.232

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents