The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
The table provides a project with the task lengths (in days)  and precedence requirements, as well as the associated task costs, crashed time, and crash costs.    -What is the crash costs for Task A? A) $1,500 B) $1,350 C) $750 D) $800 E) $600
-What is the crash costs for Task A?


A) $1,500
B) $1,350
C) $750
D) $800
E) $600