A lean system uses 12 containers, each of which can hold 12 parts. The lead time required to round-trip one container through the system is normally 3 hours. The usual safety stock is 20%.
-If the demand rate is changed to 50 parts per hour, what would be the new container size, all else being constant?
A) 12 parts
B) 15 parts
C) 10 parts
D) 20 parts
E) Need additional information to compute the value
Correct Answer:
Verified
Q3: A lean system has the following characteristics:
Q4: A lean system has the following characteristics:
Q5: A lean system has the following characteristics:
Q6: A lean system uses 12 containers, each
Q7: A lean system uses 12 containers, each
Q9: A lean system uses 12 containers, each
Q10: A lean system uses 12 containers, each
Q11: An integrated electronic-chip manufacturer has a demand
Q12: An integrated electronic-chip manufacturer has a demand
Q13: An integrated electronic-chip manufacturer has a demand
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents