A Lean System Uses 12 Containers, Each of Which Can

Question 9

Multiple Choice

A lean system uses 12 containers, each of which can hold 12 parts. The lead time required to round-trip one container through the system is normally 3 hours. The usual safety stock is 20%.
-If the demand rate is changed to 50 parts per hour, how many containers should the system be using, all else being constant?


A) 10 containers
B) 12 containers
C) 15 containers
D) 20 containers
E) Need additional information to compute the value