An integrated electronic-chip manufacturer has a demand for a specific component of 800 parts per 8-hour day. The manufacturer wants to design a lean system using containers. The containers the manufacturer used for this component held 20 parts. It takes about 4 hours to round-trip a container from one work center to the next and back again. The manufacturer also wants to hold 10% of safety stock of this part in its system.
-How many containers should the lean system be using?
A) 5
B) 10
C) 20
D) 22
E) 30
Correct Answer:
Verified
Q6: A lean system uses 12 containers, each
Q7: A lean system uses 12 containers, each
Q8: A lean system uses 12 containers, each
Q9: A lean system uses 12 containers, each
Q10: A lean system uses 12 containers, each
Q12: An integrated electronic-chip manufacturer has a demand
Q13: An integrated electronic-chip manufacturer has a demand
Q14: An integrated electronic-chip manufacturer has a demand
Q15: An integrated electronic-chip manufacturer has a demand
Q16: An integrated electronic-chip manufacturer has a demand
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents