Istanbul Industries uses a kanban system to manage production of the MI6 subassembly. In an 8-hour day, they use 100 units per hour and use containers that can hold 23 units each. It takes 120 minutes to fill and move a container of parts to the right place on the MI6 line that is currently rated at a 15% safety factor.
-If the number of containers is reduced by 1, what would be the new required round-trip time, all else being constant?
A) 90 minutes
B) 1 hour
C) 1.8 hours
D) 2 hours
E) Need additional information to compute the value
Correct Answer:
Verified
Q24: Copenhagen Industries uses a kanban system to
Q25: Copenhagen Industries uses a kanban system to
Q26: Istanbul Industries uses a kanban system to
Q27: Istanbul Industries uses a kanban system to
Q28: Istanbul Industries uses a kanban system to
Q30: Istanbul Industries uses a kanban system to
Q31: Lady Bug Machineries uses a lean production
Q32: Lady Bug Machineries uses a lean production
Q33: Lady Bug Machineries uses a lean production
Q34: Lady Bug Machineries uses a lean production
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents