Istanbul Industries Uses a Kanban System to Manage Production of the MI6

Question 29

Multiple Choice

Istanbul Industries uses a kanban system to manage production of the MI6 subassembly. In an 8-hour day, they use 100 units per hour and use containers that can hold 23 units each. It takes 120 minutes to fill and move a container of parts to the right place on the MI6 line that is currently rated at a 15% safety factor.
-If the number of containers is reduced by 1, what would be the new required round-trip time, all else being constant?


A) 90 minutes
B) 1 hour
C) 1.8 hours
D) 2 hours
E) Need additional information to compute the value

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents