Capacity Requirements Planning

Question 26

Multiple Choice

Capacity requirements planning:


A) Utilizes the master production schedule as the source of product demand information.
B) Utilizes the same information inputs as detailed capacity planning.
C) Uses planned order releases from material requirements planning instead of the master production schedule.
D) Does not include on hand inventory in its calculation of required capacity Both A and B

Correct Answer: