In rough-cut capacity planning, available hours are calculated by
A) Multiplying required capacity per unit by the quantity in the master production schedule
B) Multiplying the standard hours available by the hours actually used
C) Dividing actual output by expected output
D) Multiplying the actual hours available by the historical utilization and historical efficiency
Correct Answer:
Verified
Q23: Costs associated with level production aggregate planning
Q24: In level production aggregate planning, when the
Q25: In level production aggregate planning the production
Q26: Capacity requirements planning:
A) Utilizes the master production
Q27: Rough-cut capacity planning:
A) Utilizes the planned order
Q29: In services, achieving the demand-capacity match often
Q30: Yield management techniques recognize that
A) Requirements will
Q31: Overbooking is used
A) As a way to
Q32: Prior to developing an overbooking policy, a
Q33: For a hotel, the best overbooking policy
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents