Which of the following is an output of MRP?
A) master production schedule
B) rough-cut capacity plan
C) planned order releases
D) bill of materials
Correct Answer:
Verified
Q21: Item A has a lead time of
Q22: To minimize the effects of uncertainty due
Q23: In fixed-period ordering technique,_.
A)the order interval is
Q24: An approach to reducing the effect of
Q25: A benefit of MRP is the _.
A)reduction
Q27: What is the process that identifies which
Q28: The changes in firm planned orders _.
A)happen
Q29: In part-period balancing lot-sizing technique,_.
A)the order interval
Q30: Which file contains data about materials,components,parts,and the
Q31: The changes in a net-change MRP system