The changes in firm planned orders ______.
A) happen automatically upon changes to conditions
B) require approval from senior managers
C) can be made by supervisors on the production floor
D) can be made by customers alone
Correct Answer:
Verified
Q23: In fixed-period ordering technique,_.
A)the order interval is
Q24: An approach to reducing the effect of
Q25: A benefit of MRP is the _.
A)reduction
Q26: Which of the following is an output
Q27: What is the process that identifies which
Q29: In part-period balancing lot-sizing technique,_.
A)the order interval
Q30: Which file contains data about materials,components,parts,and the
Q31: The changes in a net-change MRP system
Q32: Which of the following is an input
Q33: Which of the following reports can be