An Activity X has a duration of 5 weeks and is budgeted to cost $12,000.The crash time for this activity is 3 weeks and is expected to cost $32,000.The cost slope for Activity X is given by ______.
A) (32,000 - 12,000) divided by (5 - 3)
B) (5 - 3) divided by (32,000 - 12,000)
C) 32,000 divided by 5
D) 12,000 divided by 3
Correct Answer:
Verified
Q14: The variance for a project's duration is
Q15: A Z value of 0.72 corresponds to
Q16: The formula for the variance of the
Q17: Whether we should crash an activity or
Q18: According to the operations profile at the
Q20: A project's standard deviation is _.
A)the square
Q21: Establishing the project's baseline requires _.
A)the work
Q22: The slope for each activity gives _.
A)combinations
Q23: In considering whether we should crash a
Q24: Projections about how much the project will
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents