Solved

An Activity X Has a Duration of 5 Weeks and Is

Question 19

Multiple Choice

An Activity X has a duration of 5 weeks and is budgeted to cost $12,000.The crash time for this activity is 3 weeks and is expected to cost $32,000.The cost slope for Activity X is given by ______.


A) (32,000 - 12,000) divided by (5 - 3)
B) (5 - 3) divided by (32,000 - 12,000)
C) 32,000 divided by 5
D) 12,000 divided by 3

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents