Whether we should crash an activity or not depends on ______.
A) crashing costs per day
B) whether the activity is on a critical path
C) both A and B
D) neither A nor B
Correct Answer:
Verified
Q12: If the most optimistic and pessimistic times
Q13: In the formula for the expected duration
Q14: The variance for a project's duration is
Q15: A Z value of 0.72 corresponds to
Q16: The formula for the variance of the
Q18: According to the operations profile at the
Q19: An Activity X has a duration of
Q20: A project's standard deviation is _.
A)the square
Q21: Establishing the project's baseline requires _.
A)the work
Q22: The slope for each activity gives _.
A)combinations
Unlock this Answer For Free Now!