Solved

If the Cost Slope for an Activity Is $10,000 Per

Question 10

Multiple Choice

If the cost slope for an activity is $10,000 per week,this means ______.


A) the activity will cost $10,000 for each week that it is accelerated
B) the primary firm will pay the contractor $10,000 for each week that the project is completed ahead of schedule
C) the contractor will have to pay the primary firm $10,000 for each week beyond the expected date of completion
D) the project leader will incur a penalty of $10,000 for each week that the project takes beyond expected date of completion

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents