If the cost slope for an activity is $10,000 per week,this means ______.
A) the activity will cost $10,000 for each week that it is accelerated
B) the primary firm will pay the contractor $10,000 for each week that the project is completed ahead of schedule
C) the contractor will have to pay the primary firm $10,000 for each week beyond the expected date of completion
D) the project leader will incur a penalty of $10,000 for each week that the project takes beyond expected date of completion
Correct Answer:
Verified
Q5: If the standard deviation is 2.78 and
Q6: Which of the following statements is true
Q7: The Z value corresponding to a probability
Q8: The formula for the expected duration of
Q9: Which of the following is NOT one
Q11: Let us say that x is an
Q12: If the most optimistic and pessimistic times
Q13: In the formula for the expected duration
Q14: The variance for a project's duration is
Q15: A Z value of 0.72 corresponds to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents