Which of the following statements is true of the earned value management (EVM) method?
A) It helps us see how the project is truly performing.
B) It links the project's schedule and costs with the work actually completed on it.
C) both A and B
D) neither A nor B
Correct Answer:
Verified
Q1: If an activity cannot be shortened,then _.
A)the
Q2: In calculating the time-cost trade-off combinations for
Q3: When we consider crashing a project,we need
Q4: We may need to consider noncritical activities
Q5: If the standard deviation is 2.78 and
Q7: The Z value corresponding to a probability
Q8: The formula for the expected duration of
Q9: Which of the following is NOT one
Q10: If the cost slope for an activity
Q11: Let us say that x is an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents