In calculating the time-cost trade-off combinations for a project's crash options,the slope for each activity is given by ______.
A) the ratio of the (crash cost less normal cost) to (normal time less crash time)
B) the ratio of the (normal time less crash time) to (crash cost less normal cost)
C) the product of the (crash cost less normal cost) and (normal time less crash time)
D) the sum of (crash cost less normal cost) and (normal time less crash time)
Correct Answer:
Verified
Q1: If an activity cannot be shortened,then _.
A)the
Q3: When we consider crashing a project,we need
Q4: We may need to consider noncritical activities
Q5: If the standard deviation is 2.78 and
Q6: Which of the following statements is true
Q7: The Z value corresponding to a probability
Q8: The formula for the expected duration of
Q9: Which of the following is NOT one
Q10: If the cost slope for an activity
Q11: Let us say that x is an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents