Project planning teams use project life cycle models because various types of projects have differing demands.Which of the following sequences of stages is most appropriate for a life cycle model for construction projects? 


A)  define - measure - analyze - improve - control 
B)  concept definition - demonstration - development - production 
C)  pre-planning - design - procurement - construction - start up 
D)  concept - requirements - design - code - test - turnover