Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the six tasks that make up the job are 4, 6, 7, 2, 6, and 5 minutes, and the cycle time is 10 minutes?
A) 3
B) 5
C) 6
D) 8
E) None of these
Correct Answer:
Verified