Solved

An Activity Has an Optimistic Time Estimate of 25 Days,a

Question 22

Multiple Choice

An activity has an optimistic time estimate of 25 days,a most likely estimate of 29 days,and a pessimistic estimate of 34 days.What is the expected duration of the activity?


A) Less than 31 days but greater than or equal to 29 days
B) Less than 29 days but greater than or equal to 27 days
C) Less than 27 days but greater than or equal to 25 days
D) Less than 25 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents