Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity) .Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?
A) 34
B) 38
C) 42
D) 48
Correct Answer:
Verified
Q20: An activity has an expected duration and
Q21: Preceding activities are those that must occur
Q22: An activity has an optimistic time estimate
Q23: The length of time expected to complete
Q24: An activity has an optimistic time estimate
Q26: At a merge point in a forward
Q27: Project Test Bank is composed of
Q28: The variance of an activity is given
Q29: An activity has a pessimistic time that
Q30: Activity Z has estimates a = 5,b
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents