When involved in a project involving many subcontractors:
A) It is imperative that the network is a mutually accessible document.
B) One subcontractor's network diagram should never be shown to another for ethical reasons.
C) PERT/CPM should not be used.
D) It is illegal to reveal one subcontractor's plan to another.
Correct Answer:
Verified
Q86: What are the strengths and weaknesses of
Q87: Most activity estimations using PERT methods lead
Q88: Mick has a project consisting of
Q89: Determine early start and early finish times
Q90: Mick has a project consisting of
Q91: How might a project manager alter a
Q92: Dummy activities are used in AOA networks
Q93: The BEST approach to network representation of
Q94: Networks are adaptable and useful for all
Q95: What are four criticisms and caveats to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents