The following are distinguishing characteristics of retrospectives methodology EXCEPT
A) It uses an independent facilitator.
B) It establishes in-process learning gates during the project life cycle.
C) An owner, typically a team member, is assigned.
D) Reviews cannot be linked to percent complete.
E) A repository is developed that is easy to use.
Correct Answer:
Verified
Q31: Completing Team Evaluations relies upon _ to
Q32: More and more companies are discarding the
Q33: Obtaining _ is a major and critical
Q34: Projects in process may need to be
Q35: When a project is completed early with
Q37: When conducting post-project audits, this is one
Q38: It is imperative that the closure facilitator
Q39: The typical mechanism for the evaluation of
Q40: A guide who leads the project team
Q41: The _ feedback approach gathers anonymous feedback
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents