You have just performed a Single Time Estimate CPM analysis and have found that more than one path through the project network has zero slack values.What can you conclude?
A) You have incorrectly performed the analysis
B) You have multiple critical paths
C) Only one path is optimal
D) More than one path is optimal
E) The project will not be completed by the desired time
Correct Answer:
Verified
Q62: If you have an optimistic time of
Q63: If the pessimistic duration of an activity
Q64: For an activity in a Single Time
Q65: A company must perform a maintenance
Q66: A simple project listing of five
Q68: You have the following time and
Q69: You have just computed a Z=2.55 in
Q70: A listing of immediate predecessor activities is
Q71: A company wants to use CPM analysis
Q72: A simple project listing of five
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents