A company wants to use CPM analysis to manage their project.One of the activities that make up the project has an uncertain duration.Three estimates have been given to determine this activity's duration.The estimates are optimistically 1 hour,most likely 5 hours and pessimistic 6 hours.Using the three activity time estimation procedure for CPM,what is the expected time this activity will take?
A) 2.5 hours
B) 3.5 hours
C) 4.5 hours
D) 5.5 hours
E) None of the above
Correct Answer:
Verified
Q66: A simple project listing of five
Q67: You have just performed a Single Time
Q68: You have the following time and
Q69: You have just computed a Z=2.55 in
Q70: A listing of immediate predecessor activities is
Q72: A simple project listing of five
Q73: You ask your subordinates how long it
Q74: Below are the data for a
Q75: You are working on a project that
Q76: You have determined the critical path in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents