You have determined the critical path in a CPM analysis.You would like to determine the probability of completing the project is a desired period of time.One of the activities on the critical path has an optimistic time of 5 minutes,a most likely time of 6 and a pessimistic time of 17.What is the variance estimate of this activity?
A) 0.5
B) 1
C) 2
D) 3
E) 4
Correct Answer:
Verified
Q71: A company wants to use CPM analysis
Q72: A simple project listing of five
Q73: You ask your subordinates how long it
Q74: Below are the data for a
Q75: You are working on a project that
Q77: If you have an optimistic time of
Q78: For an activity in a Single Time
Q79: A company must perform a maintenance
Q80: If the pessimistic duration of an activity
Q81: An assumption of three-activity-time CPM analysis is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents