A company must perform a maintenance project consisting of seven activities.The activities,their predecessors and their respective time estimates are presented below:
Using the Single Time Estimate CPM procedure,which activities make up the critical path?
A) A,B,D,F,G
B) A,C,E,F,G
C) A,C,B,F,E
D) A,D,E
E) None of the above
Correct Answer:
Verified