For an activity in a Single Time Estimate CPM analysis the Early Finish time is 20 and the Late Finish time is 20.Which of the following statements is true?
A) The activity's late start must happen before its early start
B) The activity is on the critical path
C) The slack for this activity is 20
D) The duration of this activity is zero
E) The duration of this activity is 20
Correct Answer:
Verified
Q63: In CPM analysis, it is generally expected
Q73: You ask your subordinates how long it
Q74: Below are the data for a
Q75: You are working on a project that
Q76: You have determined the critical path in
Q77: If you have an optimistic time of
Q79: A company must perform a maintenance
Q80: If the pessimistic duration of an activity
Q81: An assumption of three-activity-time CPM analysis is
Q82: Below are the data for a Time-Cost
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents